DSN Radio Astronomy
cm-Wave RF & Receivers

Manuel Franco
Last updated by Tom Kuiper on 1998 Oct 26

1998 Oct 2

The YIG wideband tunable filter is ready for testing. SEE ATTACHED DESIGN. (The diagram was in a .vsd file which we can't read -- TBHK). The design is not complete, I need to show where the drivers are connected to and to draw the second YIG Filter. The demo unit can be field tested without the coaxial switch drivers, I have ordered the drivers and as soon as they come in I will installed them, this will allow to switch the filter in and out via GPBI. I delivered a spare Iotech Interface box to Randy Rose, this Iotech can be use to test the demo unit. Let me know if you want to start the testing at DSS-14?

I am delivering the DSS-14 K-Band Maser pump to Leroy Tanida next week.

MMS-2 returned from repair. I will build a J-box to distribute 321.4 MHz and the 100 MHz, I need the MMS here for two weeks, is this a problem?

1998 Oct 9

The post amplification box from DSS-63 is under modifications. The power supplies will be installed in a separate aluminum box, and the outputs will be changed to a different side of the box.

A J-box to distribute 321.4 and 100 MHZ from and to the MMS's is under construction.

1998 Oct 19

Work continues on DSS-63 K-band post amplification assembly. Brackets to install 5 power supplies in a Hoffman box were fabricated.

Soft cables, hardlines and a box was fabricated for the MMS's IF distribution.

1998 Oct 23

Work continues on DSS-63 K-band post amplification assembly.

The MMS's IF distribution junction box is completed. The MMS and IF distribution junction box will be ship to DSS-63 as soon as the post amplification assembly is complete.

Participated in a K-band at DSS-13 implementation meeting.

1998 Oct 30

The YIG wideband tunable test filter rack mount chassis was delivered to Randy Rose and Paul Dendrenos. A schematic diagram and interfacing cable were attached to this chassis. The cable was made to connect the test filter to the Iotech box. Some items with long lead times need to fabricated to install the DSS-14 K-band HEMT package at DSS-14. Fabrication will start in the next two weeks.

1998 Nov 13

The post amplification, phase calibration and noise diode assemblies were removed from the DSS-14 XKR Cone. The assemblies will be upgraded.

1998 Nov 20

The phase calibration assembly for DSS-63 has been repaired and bench tested. Bob Hamell is performing further testing.

1998 Nov 25

The phase calibration assembly for DSS-14 is under testing by Bob Hamell.

1999 Jan 22

MMS number 2 was sent to DSS-63 under shipper no V-01744.

Ordered two Ka-band mixers for the dual-polarization Zeeman experiment.

1999 April 9

The Post amplifier and calibration assembly for DSS-63 was shipped along with other test equipment and cables. I leave for the site on Monday morning to install and do end to end testing.

1999 April 16

The K-band Instrumentation Rack installed in the cone of DSS-63 was rotated about 80 degrees towards the entrance cone door. This was necessary to provide easy access to the front and back of the rack. In doing so, four new waveguide sections were required and fabricated.

A new K-band Instrumentation Rack was provided and installed in the control-room. The electrical power is being clean-up in this rack.

I presented and discussed a detailed block diagram of the K-band Microwave to IF System to J. L. Galvez, J. A. Perea, C. Calderon, J. Hernandez, and R. Garcia.

1999 June 3

Last month the following work was performed at DSS-63:

1999 June 18

Met with L. Tanida and C. Naudet at Goldstone and discussed what is needed for Radiometry in BWG at DSS-13. Assisted in measuring the MMS internal Preselector and the external tunable filter.

1999 Jun 25

Assembled the post amplification and cal assembly power supply for DSS-14 K-band system. The cal assembly is being wired.

Submitted PR's for Iotech chassis.

1999 Jul 16

The K-band HEMT, post amplification and cal assembly were tested. Wiring errors were detected and the testing was delayed. The testing is Now complete, results are good and will be posted later this week. The system will be prepared for transportation and deliver it to DSS-14 at the end of this week. I will be looking for antenna time during the week of July 26 to install the system.

1999 Jul 30

The K-band System was installed in the cone and a cool down performed Friday afternoon. System integration and testing will be taking place this week.

1999 August 6

The waveguide interface between the K-band HEMT in the R&D cone at DSS-14 and the MMS's in the MOD III area was installed. Also, the GPIB addresses in the cryogenic thermometer and Iotech card were re-set to address 29 and 30. We ran out of antenna time, so further connections of the system will be taking place this week.

The RF plug-in of the MMS at DSS-13 was tested in the cone of DSS-14, and it was determined that the plug-in needs repair. I will send it to repair.

1999 Sep 10

The K-band System DSS-14 is installed and tested, it already supported a SVLBI Observation. The system is being tested for remote operation and minor modifications are in progress. No surprises were found, the bandpass is very similar to the bandpass at the other DSN stations.

The RF plug in from the MMS at DSS-13, that was found to be defective, is still at HP waiting to be repaired. The total cost of the repair is $ 3,100.00, NEED AN ACCOUNT NO.